Win Energy – Mazeppa Gas Plant Expansion

Gas Liquids Engineering completed engineering and regulatory work on an expansion to the Mazeppa gas processing plant to bring it from 80MMSCF/d to 90 MMSCF/d on the sour gas side (without changing the licensed inlet sulphur rate or emissions due to the current sulphur rate being lower than original design), and construct a 45 MMSCF/d train on the sweet side. Installed equipment included:

  • Two (2) 50,000 US Gallon horizontal storage bullets for LPG storage with truck loading facilities
  • New buildings
    • 3-phase inlet separator and stabilizer building
    • Sweet gas compressor building
    • Recycle compressor building
    • Refrigeration #1 building
    • Refrigeration #2 building
    • MCC building
    • Instrument air compressor building

On this website we use first or third-party tools that store small files (cookie) on your device. Our cookies are used to generate navigation usage reports. You have the right to choose whether or not to enable these cookies. By enabling these cookies, you help us to offer you a better experience. Cookie policy