Talisman Energy – Chauvin Station Truck Unloading Upgrade

Gas Liquids Engineering Ltd. (GLE) provided complete EPCM services for Talisman to upgrade the Chauvin Station truck unloading facility. Work completed included:

  • Installation of eight (8) new D-17 compliant skid mounted shop fabricated risers at CCT (dry side) and four (4) CCTF (wet side)
  • Integrate and upgrade controls, tickets, new Terminal Boss truck driver interface system
en_CAEnglish