Seven Generations – Lator 2

Gas Liquids Engineering Ltd. (GLE) provided engineering, procurement and construction support for a 250 MMSCF/d sweet natural gas processing and NGL production facility south of Grand Prairie, Alberta. Some features of the project include:

  • Efficient and cost effective project execution:
    • Low capital cost
    • 18 month project cycle time – Project start in May 2014 and start-up achieved in October 2015 (first sales gas and NGL)
    • EPCM services for less than 12% of project total installed cost
    • First IFC drawings issued and pre-fabrication of steel kicked off 6 months after project start
    • Final IFC drawings issued and site construction kicked off 10 months after project start
  • Sales NGL LACT to sales pipeline with back-up truck loading stations
  • Utilities including primary/emergency power generation, heat medium system, closed hydrocarbon drain, instrument air, high and low pressure flare systems, and 4160/480/120V power distribution
  • Sales NGL Storage – Six (6) 60,000 US gallon pressurized storage bullets
  • Large gas processing scale and scope:
    • Inlet Slug Catching and Separation
    • Dewpoint Control – Two (2) units utilizing JT-assisted mechanical refrigeration, 330 USTR chilling capacity using Howden XRV-204 refrigeration compressors equipped with 500 hp electric motors
    • Sales Gas Compression – Two (2) single-stage Ariel KBZ/4 compressor packages equipped with 3,350 hp Caterpillar G3612TALE natural gas engines
    • Recycle Gas Compression – Three (3) two-stage Ariel JGE/4 compressor packages equipped with 800 hp Caterpillar G3516TALE natural gas engines

On this website we use first or third-party tools that store small files (cookie) on your device. Our cookies are used to generate navigation usage reports. You have the right to choose whether or not to enable these cookies. By enabling these cookies, you help us to offer you a better experience. Cookie policy