Gas Liquids Engineering Ltd. (GLE) provided complete EPCM solutions for the installation of a gas battery and pipeline at Iteration Energy’s North Boundary B10-32-087-18-W6M wellsite. Installed equipment included:
- Two (2) RJV 8” Lo-Flo Separator Packages
- 2386 metre long pipeline, 114.3 mm (4 NPS) outside diameter, Grade 359 Cat 2 YJ-1