Iteration Energy – Birley Umbach a-A-80-G Tie-In

Gas Liquids Engineering Ltd. (GLE) provided EPCM services to install a gas battery at Iteration Energy’s Birley Umbach a-A‑80-G / 94-H-3 wellsite facility. Installed equipment included:

  • Two (2) RJV 8” Lo-Flo Separator Packages
  • 2933 metre long pipeline, 114.3 mm (4 NPS) outside diameter, Grade 359 Cat 2 YJ-1

On this website we use first or third-party tools that store small files (cookie) on your device. Our cookies are used to generate navigation usage reports. You have the right to choose whether or not to enable these cookies. By enabling these cookies, you help us to offer you a better experience. Cookie policy