Gas Liquids Engineering Ltd. (GLE) provided EPCM services for the Gas Unit 3 (GU3) consolidation and a new Sales Gas Pipeline installation. Project scope included:

  • New 2310 meter long Sales Gas Pipeline, 168.3 mm (6 NPS) outside diameter, CSA Z245.1, Grade 359 from 12‑16-14-08-W4M to 09‑20‑14‑08‑W4M c/w Metering Station modifications
  • GU3 Consolidation
    • Compressor K-101 and Dehydrators Decommissioned
    • Tie Compressor K-501 Discharge into existing IPC Pipeline with allowance to bypass K-501 if it is determined to be uneconomical to run
    • Convert GU3 Fuel Gas Heaters to Electric Heaters