Husky Energy – 05-09-109-08-W6M Satellite Flare Upgrade

Gas Liquids Engineering Ltd. (GLE) provided EPCM services for the installation of a new flare stack at Husky Energy’s 05-09-109-08‑W6M Satellite facility to comply with new environmental regulations. Project scope included:

  • Removal of existing 89 mm x 10.5 m high Flare Stack
  • Removal of 210 bbl Storage Tank
  • Tie-in of manual vents and drains, and test separator PSV
  • Installation of a new flare header and 114 mm x 12 m high Flare Stack c/w automatic ignition device
  • Installation of a new 3.3 m x 3.8 m x 3.7 m Flare Knockout Drum (FKOD) Skid

On this website we use first or third-party tools that store small files (cookie) on your device. Our cookies are used to generate navigation usage reports. You have the right to choose whether or not to enable these cookies. By enabling these cookies, you help us to offer you a better experience. Cookie policy