Gas Liquids Engineering Ltd. (GLE) provided EPCM services for the installation of a new flare stack at Husky Energy’s 05-09-109-08‑W6M Satellite facility to comply with new environmental regulations. Project scope included:
- Removal of existing 89 mm x 10.5 m high Flare Stack
- Removal of 210 bbl Storage Tank
- Tie-in of manual vents and drains, and test separator PSV
- Installation of a new flare header and 114 mm x 12 m high Flare Stack c/w automatic ignition device
- Installation of a new 3.3 m x 3.8 m x 3.7 m Flare Knockout Drum (FKOD) Skid