Enerplus – Medicine Hat Glauc C 2-16 Satellite

Gas Liquids Engineering Ltd. (GLE) provided EPCM services for the installation of a new satellite for Enerplus in the Medicine Hat area.

Three (3) new wells were drilled in the area, which already had five (5) existing producers. The resulting ~500 m³/d of oil emulsion required the installation of the new satellite, which was designed to handle twelve (12) wells.

Installed equipment included:

  • 30” x 10’ Vertical Test Separator Building c/w 6” Group Header, 4” Test Header, ESD Bypass System and Instrument Air Package
  • MCC Building
  • One (1) 100 bbl Pop Tank
  • 8” Pig Launcher
  • Associated Piping