Enermark – Medicine Hat Oil Battery Expansion

Gas Liquids Engineering Ltd. (GLE) provided EPCM services for the development of a water flood for the Medicine Hat Glauc C Pool, located near Medicine Hat, Alberta. Project scope included:

  • New source water (~5000 m³/d)
  • Downhole pump, wellhead, and drive
  • Flow turbine, totalizer, piping, shelter, and P/L riser
  • 13 new injection wellheads (75-250 m³/d, with a design average of 150 m³/d)
    • Willis choke valve
    • Flow turbine and totalizer
    • Pressure gauge
    • Pipeline block valve (reduction port)
    • Insulation kit
    • Small building with Ciscan heater
  • New 3” pipeline installed at each of 13 new water injection wells
  • Expansion of 3 existing oil battery’s to handle increase in produced volumes (approximately double the volume)
    • Battery 1 expansion:
      • FWKO
      • Vapour recovery / gas blanket
    • Battery 2 expansion:
      • Two (2) water settling tanks w/ vortex internals
      • Vapour recovery / gas blanket
    • Battery 3 expansion:
      • Two (2) water settling tanks w/ vortex internals
      • Two (2) water injection pumps (200 m³/day and 400 m³/day, one with VFD)
      • Vapour recovery / gas blanket

On this website we use first or third-party tools that store small files (cookie) on your device. Our cookies are used to generate navigation usage reports. You have the right to choose whether or not to enable these cookies. By enabling these cookies, you help us to offer you a better experience. Cookie policy