Champion – Vermillion Chemical Facility

Gas Liquids Engineering Ltd. (GLE) provided mechanical, civil, and structural design and construction support to expand the tank farm and upgrade the fire protection facilities at a chemical storage plant in Vermillion, Alberta. Project scope included:

  • Six (6) 70,000 litre ULC tanks for product storage
  • Four stainless steel tanks
  • Two carbon steel tanks
  • Concrete tank farm berm and liner system designed for future tank farm expansion to twelve (12) tanks
  • Catwalk system between tanks. Was designed for future tank farm expansion with catwalks to twelve (12) tank locations.
  • Six (6) pumps (100-150 US gpm each) for truck-in/out loading/offloading
  • One (1) portable pump for truck-in/out along with dedicated hoses for each chemical to reduce contamination
  • Fire water retention pond, fire water pump house, three (3) fire hydrants, and associated piping
  • Complete civil work on entire site including site drainage
  • After project completion three (3) 20,000 litre ULC tanks were purchased by the client and installed in the future tank farm expansion area. GLE updated P&ID drawings and plot plans to reflect this.

On this website we use first or third-party tools that store small files (cookie) on your device. Our cookies are used to generate navigation usage reports. You have the right to choose whether or not to enable these cookies. By enabling these cookies, you help us to offer you a better experience. Cookie policy