Cenovus – Alderson 14-28 MWB Upgrade

Gas Liquids Engineering Ltd. (GLE) provided engineering, drafting, and procurement services for Cenovus to complete wellhead modifications at their 14-28-14-14-W4M satellite location. Project scope included:

  • Re-activation of two (2) Producer Wells
  • New Risers c/w Hydraulic ESD’s and Pig Senders
  • Conversion of one (1) Producer Well to Water Injector Well
  • New Riser c/w Hydraulic ESD’s
  • New 70 metre pipeline
  • Installation of new Producer Well & Riser
  • Four (4) Full Port Ball Valves in Separator Building

On this website we use first or third-party tools that store small files (cookie) on your device. Our cookies are used to generate navigation usage reports. You have the right to choose whether or not to enable these cookies. By enabling these cookies, you help us to offer you a better experience. Cookie policy