Anderson Exploration Ltd. - Valhalla
- 3,000 bbl/d (42° API, high paraffin content) oil battery c/w treating, water source, treatment and re-injection, gas boot, gas blanket flare system, field test satellites (2) and pigging system, custody transfer metering, provision for future VRU. The solution gas plant (c/w dehydration) was designed for 6 MMSCFD. Provided permitting, engineering and project management of oil and gas production facilities including mechanical design, equipment specification, purchasing, expediting, critical path scheduling, reporting, cost control, instrumentation, controls system design. The scope of the installation also included an inlet skid, a separator package, storage tanks, a recycle building, a process heater and a PLC control system.
City of Medicine Hat, Medicine Hat
- 2,000 B/D oil battery/treating facility. Provided permitting, engineering and project management for the oil production facilities including mechanical design, equipment specification, purchasing, expediting, critical path scheduling, reporting, cost control, instrumentation, and controls system design.
Crestar Energy Inc. - Bantry
- Provided project management, equipment specification, and control and electrical systems design for a grass roots oil battery consisting of an inlet test separator, free water knockout, water injection, solution gas compressor (800 HP), and a tank farm. The control system consisted of a PLC 5/30 and Winview MMI. The power system consisted of a 1000 A service with a 200 HP gas compressor and a 125 HP water injection pump.
Crestar Energy Inc. - Saddle Hills
- Design and project management of a 2,000 bbl/d oil battery for treatment of 25° API oil including 4,000 bbl/d water injection facilities.
- Responsible for permit applications and specification and procurement of mechanical equipment, including a crude oil treater, tankage and VRU, for a 300 m³/d crude oil battery.
- Project engineering for expansion to a oil battery to include 800 HP electric driven compression, power generation (1MW), MCC building, flare stack, line heater and an inlet separator/pumping skid.